Breaking: Boeing halting 787 deliveries to Everett until June

Boeing will hold shipments of fuselage section for Airplane 23 at supplier partners to allow them to catch up, pushing the start assembly to early June, company sources confirm.

The halt in deliveries to Everett will not cease production activities at Final Assembly, the aircraft currently on the line, numbers 19, 20, 21 and 22 will continue undergoing assembly.
Program sources tell FlightBlogger that the plan is to hold deliveries for up to 24 manufacturing days, beginning at the end of this month and stretching into June. A typical month contains 22 manufacturing days with a 5-day work week. The hold is expected to last a total of four weeks and four days. 
787 production had been running at a two aircraft per month pace, accepting deliveries from Boeing Charleston and supply partners every 10 manufacturing days. Production was supposed to accelerate from two to two and a half aircraft per month beginning in August.

This post was originally published to the internet between 2007 and 2012. Links, images, and embedded media from that era may no longer function as intended.

This post originally appeared at Flightglobal.com from 2007 to 2012.